Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » SSE reaches FID on 208MW Strathy South
Onshore Wind

SSE reaches FID on 208MW Strathy South

SaraBy SaraDecember 17, 20242 Mins Read
Glennmont starts up 211MW Finnish wind

SSE has taken a final investment decision to proceed with construction of its 208MW Strathy South wind farm in the Scottish Highlands.

Development of Strathy South, which is located in north-east Sutherland, has been ongoing for over a decade.

Advertisement

Main construction works at Strathy South will begin in spring 2025, with commercial operations expected in late 2027.

Vestas has been selected to supply, install and commission the 35 V162-6.2 MW turbines for the project.

SSE Renewables will establish a community investment fund as part of the Strathy South project, which is valued at £1m per year for the lifetime of the wind farm.

In addition, Strathy South will have a vast biodiversity net gain (BNG) through the restoration of peatland at the site and the removal of over 1000 hectares of non-native commercial forestry.

Heather Donald, director of onshore wind, solar and battery at SSE Renewables, said: “While a number of external factors continue to provide significant economic challenges for the deployment of onshore wind in the UK, we’re pleased to confirm that our Strathy South Wind Farm project has now reached a final investment decision (FID) and will proceed into construction next year.

“As a project that has been in SSE Renewables’ portfolio pipeline for over a decade, this decision marks an important milestone for the project’s progression.

“Along with supporting delivery of the UK and Scottish Government’s ambitious decarbonisation and energy security targets, Strathy South will deliver a number of legacy benefits to its host communities and the Highland region throughout the project’s lifetime.”

Onshore Wind SSE Strathy South
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleSSEN Transmission gains upgrades consent
Next Article SPEN launches £10.6bn transmission plan

Related News

SSE begins construction of 208MW Strathy South

May 20, 2025

RWE prepares to launch 63MW Strathy Wood construction

January 3, 2024

Onshore wind nets 1.5GW in UK auction

September 8, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}