Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » RWE wins funding for 14MW electrolyser
Other News

RWE wins funding for 14MW electrolyser

SaraBy SaraMay 3, 20223 Mins Read
A storm gathers over the Triton Knoll offshore wind project off eastern England

RWE has secured public funding commitment for a 14MW electrolysis test plant in Lingen, in Germany.

The project is slated to start construction in June 2022 and RWE plans to invest €30m in the project with the State of Lower Saxony providing €8m.

Advertisement

The pilot plant will test two electrolysis technologies for planned large-scale hydrogen projects and could be operational from mid-2023.

The electrolysis plant will be located on the site of RWE’s Emsland gas-fired power plant.

Sopna Sury, chief operating officer for hydrogen at RWE Generation, said: “By 2030, RWE will create two gigawatts of its own electrolysis capacity to produce green hydrogen.

“The investment decision for a test facility here in Lingen is trend-setting for us.

“In this way, we want to gain operating experience in the industrial use of the two technologies, which are to be used in the three-digit megawatt range as part of GET H2, for example.

“The finding commitment of the Lower Saxony Ministry of the Environment contributes significantly to the implementation of this pilot project, which paves the way for future large-scale plants.”

Olaf Lies, Minister for the Environment, Energy, Building and Climate Protection of the State of Lower Saxony, added: “Here in Lingen, we see a fascinating history of transformation into the future of our energy production. RWE is thus not only showing that it stands by Lingen as an energy location.

“The pilot project is also the first step towards the planned development of large-scale electrolysis capacities here on site.”

RWE wants to test two electrolysis technologies under industrial conditions in the pilot plant.

The Dresden-based manufacturer Sunfire is installing a pressure-alkaline electrolyser with a capacity of 10MW for RWE.

At the same time, Linde, the world’s leading industrial gases and engineering company, is building a 4MW proton exchange membrane electrolyser (PEM).

RWE will be the owner and operator of the entire plant in Lingen.

After obtaining approval and the construction phase, the electrolysis plant will generate up to 290 kilograms of green hydrogen per hour from spring 2023 using green electricity.

The trial operation is initially designed for three years, with the option of another year.

The hydrogen produced in this way is to be fed into a public hydrogen network or added to the fuel for gas turbines of the power plant.

It could also supply the hydrogen-capable gas turbine, which RWE and Kawasaki are planning to build in Lingen by 2024.

As part of the GET H2 project, RWE plans to build a first 100MW electrolysis plant in Lingen by 2024, expanding to 300MW by 2026.

electrolyser Green Hydrogen Other News RWE
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleGDG undertakes Irish ports study
Next Article AES Solar installs PV at Edinburgh Castle

Related News

Sunfire scoops 100MW electrolyser order

September 11, 2024

RWE commissions pilot electrolyser

August 12, 2024

Orsted, BP join forces on German green hydrogen project

November 10, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}