Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Work restarts on Mocean wave device
Wave & Tidal

Work restarts on Mocean wave device

Robin LancasterBy Robin LancasterJune 22, 20202 Mins Read
Work restarts on Mocean wave device

Scottish fabricator AJS Production has returned to work to complete a 30-tonne wave power device for Mocean Energy.

The steelwork specialist has split its eight-strong team to comply with Covid-19 rules and allow them to forge ahead with the fabrication of the 20-metre long Blue Star unit.

Advertisement

The half-scale device will be deployed at the European Marine Energy Centre (EMEC) in Orkney for sea trials prior to generating first power next year.

AJS Production managing director Raymond Imrie said: “We’ve split our workforce into two teams, each working 12 hour shifts three days a week.

One team does Monday, Wednesday, Friday, the other Tuesday, Thursday, Saturday. This means we can operate at nearly 90% capacity.

“We’ve just received new monitors which vibrate if workers come withing two metres of each other, and we’re splitting breaks to ensure everyone keeps their distance.

“There is only one of our workers – who is 73 – still on furlough, but we hope he will be back soon.

“It’s really important we keep up with this work for Mocean Energy and continue with other contracts we have in the marine renewable energy sector.”

Mocean Energy managing director Cameron McNatt said: “It is great to see this can-do attitude by Raymond and his team.

“Our nacelle is now nearing completion and has gone to the paint shop, so the AJS team is now working on the main hull.

“We are looking ahead to seeing the whole device being completed and transporting it up to Orkney.

“Clearly we recognise the restrictions in place, and our focus is on doing what we can now, whilst being ready to move forward as soon as regulations allow.”

Mocean Wave and Tidal
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleUK, Norwegian JV targets wind logistics
Next Article Enlight flush for 312MW Spanish wind build

Related News

Mocean nets £2.2m for wave tech

November 13, 2023

Mocean Blue X wave device put to the test

June 14, 2021

Mocean Blue X wave device arrives in Orkney

May 14, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}