Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » COVID-19: Island trust works to keep hydro scheme on track
reMIX

COVID-19: Island trust works to keep hydro scheme on track

SaraBy SaraJune 1, 20202 Mins Read
COVID-19: Island trust works to keep hydro scheme on track

Rasaay Development Trust (RDT) has been working with Forestry and Land Scotland (FLS) to help keep a renewable energy scheme on the island on track.

The Inverarish hydro scheme is the first application of its kind to FLS’s Community Asset Transfer Scheme in order to build and operate a community owned ‘run-of-river’ hydro scheme.

Advertisement

To secure a feed-in tariff for providing power to the National Grid, the scheme has to be operational by Sept 2021.

Due to Covid-19 restrictions the community is having to make some “major adjustments” to its plans to meet the deadline, including working with FLS to reschedule some harvesting work.

RDT chair Iain Ross said: “Sustainable energy solutions will help us tackle fuel poverty on the island and strengthen our continuity of supply while helping us fulfil our commitment to safeguard our environment for future generations.

“The hydro scheme will improve the resilience of our community, giving us access to power, reducing our reliance on imported fossil fuels and establishing a small income stream that can fund other projects and contribute to a community benefit fund.

“In this initiative RDT is being supported and funded by Scottish Government’s Community and Renewable Energy Scheme (CARES) and private match funding (Community Benefit Grant) which has also been secured for the project.

“We have now received planning permission, have the necessary CAR licence from SEPA, are pre-accredited with Ofgem and have a valid grid offer from SSEN.

“The current Covid-19 restrictions have meant some re-arranging and fine tuning of timescales, but we believe that we can quickly build momentum when things return to something near normality. We believe this is only a pause and minor inconvenience considering the longer-term sustainability benefits this project will deliver for the island.”

The renewable energy scheme sits within RDT’s five-year development plan.

Forestry and Land Scotland north region manager Graeme Prest said: “Covid-19 restrictions meant we all had to have a bit of a re-think, both to make the necessary adjustments, and to assess what could be done to keep the project moving forward and be ready to get cracking once restrictions ease.

“We’ve made alterations to our proposed felling works to align them with RDT’s plans so that construction can go ahead as soon as possible in line with Scottish Government guidelines and still meet the FiTs deadline.”

Hydro reMIX
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleMingYang installs storage tech at Huian Quanhui
Next Article The final GE Renewable Energy turbine has been installed at the 102MW Kipeto wind project in Kenya.

Related News

New Celtic Sea wind resource model unveiled

July 12, 2024

Mainstream, Someva win Oz wind giant permit

May 23, 2024

Banks back Scottish community hydro scheme

June 22, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}