Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Sykes: CfD to COD needs laser-sharp delivery focus
reMIX

Sykes: CfD to COD needs laser-sharp delivery focus

Stephen DunneBy Stephen DunneFebruary 12, 20265 Mins Read
Sykes: CfD to COD needs laser-sharp delivery focus

2026 has got off to an attention-grabbing start for UK offshore wind, writes Orsted head of UK Benj Sykes (pictured).

Last month’s AR7 results speak for themselves, with more than 8GW of CfD-bearing projects added to Britain’s burgeoning offshore wind sector, alongside the 16.6GW already delivering power to the grid, and 11.7GW in construction.

Advertisement

The results mark another step towards a clean, secure and diverse future energy system but those CfDs  mark the firing of the starting gun – with much work to be done to reach the finish line. Contracts for Difference are just that; contracts. We now need to see them delivered on time and on budget, and as a sector we must be sharper than ever on execution, as well as continuing to mature the pipeline of projects for the future.

If the last few years in the offshore wind industry have taught us anything, it is that the goal for everyone involved in delivering offshore wind must be: first, to rapidly deliver good-value, secure renewable power onto the system to ensure consumers can benefit as quickly as possible. Second, to achieve an end-to-end system which allows developers to bid competitively in CfD auctions – this requires confidence that projects can be delivered on time and in line with assumptions made in the business case.

We have some amazing projects in construction in the UK offshore wind sector including our own Hornsea 3, East Anglia 3, Sofia and the A, B and C zones of Dogger Bank Wind Farm. But the challenges of construction and commissioning are becoming all too evident, and much work remains to be done to predictably turn contracts into generating assets.

This is all to say that allocation rounds are important – they’re a large part of what’s put Britain in a leading position in offshore wind – but there are many more factors at play when delivering these complex projects.

We at Ørsted are not immune to these types of challenges. We have had to make tough decisions, including putting Hornsea 4 back into development, meaning we know that being awarded a CfD is not the end – merely the end of the beginning.

Looking forward, our Hornsea 3 Offshore Wind Farm will make a huge contribution to the UK’s home-grown renewable energy as well as our energy security. The onshore element of this £8.5bn project is progressing well and this year we start offshore construction.

The execution of such a large and complex project is only possible because of seamless integration between our project team and our supply chain partners. We must never underestimate the experience and skill necessary to deliver the world’s single largest offshore wind farm, coordinating the multitude of contractors and sub-contractors working across all scopes. Work is also split between different suppliers, depending on expertise and size of scope, with, for example, array cables being supplied by both Prysmian and Hellenic and the cable protection system by Balmoral. For monopile production, due to the 197 required we are working with 4 different suppliers: Dajin, EEW, Haizea and Steelwind.

The extent and range of production for such a large project calls for a variety of different manufacturers. This allows us to manage risks around our schedule and milestones as a project of this size and complexity has many moving parts, all of which are reliant on one another.

Of course, risks to large and complex offshore wind farm construction projects don’t just come from the supply chain. For these projects to move from CfD to COD the whole infrastructure of execution needs to perform reliably and predictably. This includes the vital elements of timely grid delivery and the ongoing, timely delivery of consents. The need to move from words to tangible actions has never been more pressing –if developers are to build the wind farms needed for the government to reach its ambition of 95% clean power generation by 2030. Against that backdrop, it’s clear that delays or uncertainty are extremely unhelpful – for example the announcement of NESO’s Connections Reform process was warmly welcomed by the industry. However this process is now stalled which is not helpful for projects that are already in progress and scheduled to deliver power in the next couple of years.

Building national infrastructure projects like offshore wind farms requires a complex ecosystem of consenting, grid, supply chain, community engagement and a range of other factors to deliver what is needed at precisely the time it is required. And as I’ve said, time is the crucial element here as unforeseen delay in any piece of the puzzle introduces both risk and cost, which is why the latest news on Connections Reform is so problematic for the sector. For us and for the industry, 2026 is a pivotal 12 months that will determine how the UK continues to scale up the delivery of offshore wind responsibly to meet the UK’s energy and economic needs. Long-term success depends on the right conditions to ensure the UK retains its global leadership.

So, what are those conditions?

To deliver the next generation of projects, there are some key requirements for success:

· An efficient and predictable planning system, with strong environmental protections built in, that is designed to avoid disruption to the construction schedule post FID.

· Delivery of a modern, flexible and resilient grid capable of connecting and integrating large volumes of renewable power on time. It is vital that projects moving through the system can rely on their grid connections to ensure that the renewable energy they generate can reach homes and businesses across the UK.

· Support for a competitive, innovative supply chain that can grow with the industry.

· Industry working closely and collaboratively with communities, to the benefit of both.

Success comes not just in awarding and winning bids but in building and then operating our windfarm fleet. We look forward to playing our part and working with Government and industry colleagues to deliver for Britain.

Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleCollett completes Stranoch turbine deliveries
Next Article Great British Energy confirms Aberdeen HQ

Related News

CIP secures 245MW Romanian wind CfD

March 13, 2025

UK plans CfD reforms to boost offshore wind

February 21, 2025

APAC supply chain ‘not up to scratch’

November 25, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Pembroke Port
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}