Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » North Yorkshire solar scheme wins appeal
Solar

North Yorkshire solar scheme wins appeal

SaraBy SaraJune 29, 20232 Mins Read
Cero Generation finances 48MW solar farm in Italy

A 50MW solar development in North Yorkshire has been successful in an appeal against an earlier refusal of the scheme by a local council.

Developer Lightrock Power lodged the appeal against the decision by Hambleton District Council which refused the scheme, in Scruton, on the basis of the impact on agricultural land.

Advertisement

According to the appeal documentation, the inspector found that the majority of the land was not BMV (DL18), but that even if it was, it wouldn’t be “lost”, and neither the development plan nor national policy prevented the use of such land.

The council’s case at the hearing was that the loss of productivity of the land for the 40 year duration of the scheme was objectionable, but the inspector noted that “the specific way agricultural land is used is not a matter that is subject to planning controls…Given this, the fact that the proposal would limit the ability to carry out any arable farming does not, in my opinion, mean that it results in the loss of agricultural land when it can still be used for other agricultural uses.

“Furthermore, current government schemes actually encourage farmers to take land out of production and put it to grass, meadows, or trees for carbon capture.” (DL22).

The inspector recognised the scarcity of grid connections nationally, and the fact the site benefited from an immediate grid connection to the nearby substation.

The proposed development would make a valuable contribution to achieving local and national renewable energy goals as well as achieving a substantial biodiversity net gain.

Costs were awarded on the basis the council failed to produce relevant evidence to support the RFR, and so delayed development that should have been permitted.

Solar
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleStorage tech to produce ‘carbon-neutral’ whiskey
Next Article Connection backlogs delaying US renewables expansion

Related News

Enviromena to appeal Marr solar refusal

December 17, 2025

Enviromena wins appeal for 40MW solar farm

December 15, 2025

Boom Power wins English solar farm appeal

September 13, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}