Structure is the first of 62 for the 496MW French offshore wind farm
Activities will mobilise up to 30 vessels for several months with first turbines to be installed in mid-2023
Cable installation due to take place this month with drilling, pile work scheduled for first quarter 2023
The companies will do the assembly work before the masts are transported onsite
The Saipem 7000 vessel carried out the work at the 496MW French offshore wind farm
Work has now started on the installation of the second jacket at the northern part of the wind park
Each jacket weighs 1150 tonnes, is 75 metres high and 25 metres square
First four support structures out a total of 62 are being transported from north-west Spain to France
Iberdrola using Wavex’s virtual sensor tech to measure current speeds which exceed 1 m/s on a daily basis
The Navantia Fene shipyard today began shipping the first 4 Jackets of the 62 contracted in consortium with Windar for…