Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Energinet delay rate drops to 69%
Other News

Energinet delay rate drops to 69%

Web EditorBy Web EditorDecember 8, 20252 Mins Read
Energinet delay rate drops to 69%

Energinet’s latest quarterly report shows 69% of its electricity and gas transmission projects are now delayed or postponed, down from 73% in Q2 2025.

The operator said the improvement reflects delayed projects being commissioned and new projects entering the pipeline.

Advertisement

It added that average postponements on delayed schemes have increased to 29 months.

“We are constantly working hard to ensure progress for our projects with the tools we have in Energinet,” said chief operating officer Soren Dupont Kristensen.

He noted that the portfolio is evolving and that future quarters may show a different picture.

Energinet had 203 transmission projects in the establishment phase in Q3, including 192 electricity grid schemes.

It stated that 14 projects changed timetable, with four advancing and 10 facing longer schedules.

The company said extended timelines stem from long environmental and municipal processing periods, developers postponing their own components, and supplier or internal challenges.

Energinet reported that older projects are particularly exposed as assumptions from decisions made 5–10 years ago have shifted amid faster renewable expansion and longer component delivery times.

The operator highlighted that environmental screening periods have risen from about 100 days in 2020 to around 800 days.

It added that schedules for 98 projects were extended in 2024 by more than one year on average after it reassessed timelines.

Energinet has launched several initiatives to reduce delays, though many will mainly benefit new projects.

To ensure better reporting of delays and postponements, Energinet said it has made a minor adjustment in the calculation method since the last quarterly statement and removed nine maturation projects from the inventory and added six establishment projects under DKK 10 million (€1.3 million).

delay rate drop Energinet longer overrun quaterly
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleRecord battery discharge supports Irish power system
Next Article Enshore lands German offshore cable work

Related News

Energinet drops queue rule for faster connections

November 27, 2025

Energinet pilots local flexibility markets

February 22, 2021

Energinet starts Hesselo survey campaign

October 2, 2020
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}