Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » First new Dinorwig cables power up
Hydro

First new Dinorwig cables power up

SaraBy SaraMarch 10, 20252 Mins Read
First new Dinorwig cables power up

The first of three new sets of power cables connecting Dinorwig hydroelectric power station in north Wales to the transmission network has been energised.

Engineers from National Grid, and contractors Morgan Sindall Infrastructure and Siemens Energy, reached the key milestone as part of the Dinorwig to Pentir project to replace cables originally installed in the 1970s, and which are now coming to the end of their operational life.

Advertisement

Dinorwig power station is owned and operated by First Hydro, a company which is 75% owned by Engie.

Since autumn 2021, National Grid has been upgrading the 12 km connection between its 400kV Dinorwig substation – which sits inside the same mountain as the power station, transmitting its electricity to the grid – and its 400 kV Pentir substation.

The first new circuit, comprising three 12.2km cables each made from 14 sections joined together and weighing an estimated 1,500 tonnes, has been installed under sections of the A4086 and A4244, in nearby fields and inside Dinorwig.

Each new circuit takes a different route from the original cables, ensuring the existing connection can remain in service and continue transmitting vital clean power from Dinorwig while the upgrades take place.

Alongside installing the new underground electricity cables, National Grid is also making good progress on major upgrades to its Dinorwig substation.

Phil Rose, National Grid’s Lead Project Manager for the Dinorwig to Pentir cable replacement project, said: “Completing the first of our three connections marks a really significant milestone in this crucial project to futureproof the infrastructure carrying clean power from Electric Mountain.

“It’s also a fantastic achievement for the team despite some very difficult conditions, with extremely hard rock and unprecedented rainfall challenging our progress at times.

“We appreciate the cooperation and understanding of the local community whilst the work takes place, and want to thank everyone locally for their continued patience while this essential work progresses.”

Peter Kirk, Managing Director, Energy at Morgan Sindall Infrastructure, said: “Energising circuit 3 at Dinorwig-Pentir creates a more resilient power network for the UK.

“This improvement will enable the network to better handle sudden changes in power demand and unexpected outages, and also supports the UK’s net zero carbon goals by providing vital infrastructure needed for renewable energy sources.”

Hydro National Grid
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article‘Residents near new pylons face lower bills’
Next Article Infinis hires new CEO

Related News

National Grid energises second Dinorwig circuit

April 7, 2026

National Grid advances North Wales grid upgrade

January 21, 2026

National Grid launches £8bn substation drive

July 31, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}