PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » NESO to apply fee to drive connections queue
Grid

NESO to apply fee to drive connections queue

SaraBy SaraFebruary 10, 20253 Mins Read
NESO to apply fee to drive connections queue

The UK’s National Energy System Operator (NESO) is to introduce a new Progression Commitment Fee to support the future connections queue.

The proposed fee, to occur through modification of the Connection and Use of System Code (CUSC), will augment the connections reforms under consideration by the energy regulator Ofgem.

Advertisement

Following a call for input with industry in October 2024, NESO has revised its initial proposal to better balance industry concerns with a requirement to motivate future projects to continue to progress through the connections queue, or to exit at the earliest possible opportunity.

The proposed fee will not immediately be applicable but instead will be subject to a defined activation trigger.

If activated, NESO’s proposal would mean that project developers would be exposed to a fee payable on termination or reduction in capacity, with the fee payable increasing over time.

Under the reformed connections process the proposed fee would provide an additional incentive for developers to regularly assess the viability of their projects during the period before they submit their planning applications.

The proposed fee would only be applicable to projects that have advanced through the initial stages of the connections process to enter the future Gate 2 connections queue but have not yet submitted their planning consent application.

NESO’s proposal is that initially, the fee would be equivalent to an additional £2500/MW for the project and would increase by an additional £2500/MW every six months, up to £10,000/MW, during the time a project is in the Gate 2 queue without a submitted application for planning consent.

Kayte O’Neill (pictured), Chief Operating Officer, National Energy System Operator, said: “Ensuring that we have effective measures to make connections reform a success is critical to the future of the electricity network.

“The proposed Progression Commitment Fee will maintain the impetus for projects to regularly assess the viability of their project. It will support wider reforms, as another tool to speed up the connections process, deliver the electricity needed for 2030 and beyond.”

Energy Secretary Ed Miliband said: “Speculative energy projects have been left to linger in the grid connections queue for too long, while viable projects that can help us deliver clean power by 2030 face frustrating waits of many years in some cases.

“As a next step to deliver our Clean Power Action Plan, these sensible measures will encourage developers to stick to deadlines and only bring forward their most progressed projects so we can accelerate Great Britain towards a new era of clean electricity.”

Grid NESO
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleAll-Energy 2025 opens for registrations
Next Article Aker wins BalWin 1&2 foundations deal

Related News

NESO opens window for new grid connections

July 8, 2025

NESO sets out timeline for connections reform

June 10, 2025

NESO to ‘pause’ grid connection bids

January 15, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}