Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Race for bigger turbines ‘paralyses’ suppliers
Offshore Wind

Race for bigger turbines ‘paralyses’ suppliers

reNEWS EditorialBy reNEWS EditorialNovember 22, 20243 Mins Read
Spaniards float Japanese plans

The “rat race” to build ever-larger turbines is paralysing the offshore wind supply chain, according to global consultancy Roland Berger.

Europe has chosen offshore wind as a key pillar of its energy transition. The offshore wind sector has pledged to ramp up its capacity from 7 to 20GW/year to realise the target of 120GW capacity in 2030.

Advertisement

However, these objectives are under pressure as the offshore wind supply chain is currently in an impasse, Roland Berger claims in a new report.

Partner at Roland Berger Bram Albers said: “The offshore wind industry must triple its capacity. Now is the time to lay the groundwork for a robust, future-proof supply chain, to ensure competitive cost of electricity and continued industrial activity in Europe.”

The report warned that while governments are organising competitive tenders for wind farms, which increases cost pressures, project developers often opt for the largest turbines to save money. This means turbine manufacturers are engaged in a race to develop ever-larger turbines to increase their market share.

Previously, this approach resulted in lower costs, as larger turbines require fewer units to generate the same amount of energy. However, the current size of these turbines means that further increases yield relatively little cost advantage, Roland Berger said.

It warned that this “rat race” towards larger turbine models has had the opposite effect: the supply chain for components, such as gearboxes and foundations, lacks clarity about the future size of turbines, leading to hesitance in investing in new factories.

The report said contractors responsible for turbine installation are also uncertain about the size of their cranes, which deters them from ordering new vessels. Meanwhile, ports need to know at which depth to construct their quays.

This all results in significant delays in offshore wind deployment and substantial price increases due to supply chain shortages, the report warned.

The industry has been discussing the establishment of a standard for turbines for several years. The Dutch wind energy association, NedZero, proposes setting a maximum height for turbines, but to date, no standard has been implemented.

Senior associate at Roland Berger Maarten de Vries said: “To halt the increasingly fruitless rat race towards bigger turbines, we need to set an industry standard for turbine size, and to do so for long enough that the European offshore wind industry can build the robust, industrialised supply chain it needs.

“Additionally, it is important for the industry to collectively develop a roadmap to eventually transition to even larger and/or smarter turbines.

“Only with such a roadmap for the innovation of offshore wind turbines can the industry prolong its global competitiveness into the future.

“Only then can Europe achieve its energy transition in a timely and cost-effective manner.”

Offshore Wind Renewable energy news roland berger
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleScope Award is a hat-trick for KGAL
Next Article Statkraft inaugurates 100MW Chilean trio

Related News

‘Turbine arms race driving failure rates higher’

May 3, 2023

Floating wind ‘key to cheap green hydrogen production’

June 29, 2021

Vattenfall team prepares for solar race

February 5, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}