Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » ‘Sweden must speed up permitting’
Offshore Wind

‘Sweden must speed up permitting’

reNEWS EditorialBy reNEWS EditorialApril 22, 20243 Mins Read
Mayflower unveils Massachusetts bid details

Statistics from Swedish Wind Energy highlight concerns the country’s government’s work to speed up and improve the permit process for both onshore and offshore wind power needs to pick up pace. 

New statistics from Svensk Vindenergi on the expansion of wind power in Sweden shows that five investment decisions were made for new wind power during the first quarter of the year. 

Advertisement

A total of 222MW of new turbines were ordered during this period. 

The investment decisions are made for projects that have received all their permits, but the outlook is less hopeful in terms of the pace of how many new projects are getting permits. 

The reform pace for more predictable and shorter permit processes needs to increase if we are to complete Sweden’s electrification by the year 2030 in order to be able to meet Sweden’s climate goals by the year 2045, according to the association.

Erik Almqvist, who is responsible for the electricity grid and electricity market at Svensk Vindenergi, said: “It is gratifying that investment decisions continue to be made for new wind power in Sweden, but we see that the expansion of electricity production in the coming years risks losing speed and volume.

“If that happens, the obvious risk is that it will not be possible to meet the industry’s increasing electricity needs in the next 10 years. 

“A concern is seriously building that there will not be enough new permits for both onshore and offshore wind power quickly enough through the Swedish permit process.”

Swedish Wind Energy’s compilation of wind power projects in the permit process shows that the industry is prepared to respond to the industry’s increased electricity needs by projecting 17GW of wind power on land and 106GW offshore, but so far only 4GW or 2GW granted permission.

To shorten the permit process now, political proposals and initiative are needed, the organisation argued.

The rule changes that have already been investigated regarding the municipal veto and compensation for nearby residents – in combination with a clear financial government incentive for municipalities that contribute to electrification – need to be put in place quickly, it added. 

Furthermore, Swedish Wind Energy said the government needs to make positive decisions about the offshore wind farms that are awaiting notification and not wait for investigation reports.

Without clear political signals about the importance of an increased pace in wind power expansion, there is a risk that Sweden will become less attractive to invest in, it warned.

Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleGreen light for Oz wind farm
Next Article Orsted contracts OEG for US projects

Related News

Sweden grants permit to just three wind farms in 2025

March 16, 2026

Concern at barriers to wind development in Sweden

May 12, 2025

‘Turbine orders dropping in Sweden’

April 29, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Pembroke Port
  • Ørsted
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}