Nordex has received a 264MW turbine order from UAB Renerga for a wind project it is constructing in Lithuania.
Nordex will supply 40 N163/6.X turbines, from the Delta4000 series, for the Pagegiai wind farm project in the west of the country.
The agreement also includes a servicing contract.
The infrastructure works are scheduled to start in June 2024, with the delivery and installation of the turbines scheduled to start in spring 2025.
Nordex will install the turbines on tubular steel towers – 29 with hub heights of 118 metres and 11 with hub heights of 113 metres.
The completion of the wind farm is expected in 2026.
Mindaugas Juodis, CEO of Renerga, said: “We would firstly like to sincerely thank all our partners for the smooth and efficient cooperation in the development of the Pagegiai wind farm.
“This project solidifies Renerga as the leading renewables developer in Lithuania. We expect to continue to expand our renewables portfolio going forward as has been the case from the very start of Renerga’s history in 1998.”
Patxi Landa, CSO of the Nordex Group, said: “We are very proud to be working with UAB Renerga for the first time, especially on this 264MW large-scale Pagegiai project.
“We see the supply contract as the starting point of a powerful cooperation between both groups.”
Including this new order, Nordex has sold more than 850MW since 2015 in Lithuania, with 460MW under construction.