Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Statkraft receives battery project planning permission
Energy Storage

Statkraft receives battery project planning permission

reNEWS EditorialBy reNEWS EditorialFebruary 16, 20242 Mins Read
Statkraft receives battery project planning permission

Statkraft has been granted planning permission to construct the Greener Grid Park on land adjacent to the Coylton substation in the UK, which will store energy in 50MW batteries.

The project aims to increase the stability of the electricity grid and allow more renewable power to be transmitted through the network. 

Advertisement

Stability is provided by battery technology, with grid forming converters attached, which always stay in ‘grid-forming’ mode, meaning they inherently resist changes in voltage and frequency on the electricity grid.

Meanwhile, the batteries will store, import, and export energy which will facilitate the decarbonisation of the UK’s electricity supply.

Construction of the project is expected to begin later in 2024.

Statkraft original submitted a minor planning application for Coylton Greener Grid Park in 2021, and received consent from East Ayrshire Council in August 2022, with the application receiving no objections.

At the time of submission, National Grid ESO had not confirmed their exact requirements for the project. Once these were confirmed, Statkraft then revised its plans and submitted this subsequent major planning application to reflect this.

Sarah Tullie, Statkraft’s Project Manager for Coylton Greener Grid Park said: “I want to thank East Ayrshire Council for backing our project. Greener Grid Parks are a key tool in helping the UK transition to green energy. Projects like them mean we’ll eventually end the need to turn on polluting fossil fuel power stations, just to provide stability to the electricity grid. 

“Having a stable grid because of projects like this will allow more wind and solar energy to be built and connected, meaning lower bills for consumers because renewable power is cheaper. Statkraft will continue to play a key role in delivering innovative solutions like this and help to break our reliance on fossil fuels for good.” 

Battery Energy Storage Greener Grid Park Grid Renewable energy news Statkraft UK
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleSiemens Gamesa to supply turbines for Baltyk 2 and 3
Next Article EBRD funds Georgia HPP modernisation

Related News

NHOA Energy to deliver Scottish battery

June 20, 2024

Statkraft gets green light for Welsh grid project

July 5, 2023

Statkraft powers up UK greener grid park

March 9, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}