Nordex secured 181MW of turbine orders in Germany in July and August for several projects.
The manufacturer is supplying 32 turbines for various customers for projects in Lower Saxony, Brandenburg, Schleswig-Holstein and North Rhine-Westphalia, among others.
The largest site is being built in Lower Saxony.
Shortly after the start of the installation of the first of 12 turbines in the 82MW Gevensleben wind farm in the Helmstedt district, the Landwind-Group has now ordered further N163/6.X machines.
Nordex will install six turbines in the 6MW class at a hub height of 164 metres at the 40MW Cramme II site in the district of Wolfenbüttel.
Construction and commissioning of the units is scheduled for 2024.
“We are delighted that our customers have placed the new orders,” said director sales region central at Nordex Group Felipe Villalon Waldburg-Zeil.
“The largest wind farm in Germany is currently being built in Gevensleben for the Nordex Group and the Landwind-Group.
“Cramme II is also an extensive project with 40MW – the Landwind-Group relies on our 6MW technology for both wind farms.”