Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » First Viking turbines installed in Shetland
Onshore Wind

First Viking turbines installed in Shetland

Eleanore RobinsonBy Eleanore RobinsonApril 14, 20232 Mins Read
First Viking turbines installed in Shetland

The first Vestas V117 turbines have now been installed at SSE Renewables’ 443MW Viking Wind Farm on Shetland.

The first turbine completed is located at South Midfield, west of Kergord, in the far southwest of the Viking site, and this was closely followed by the completion of a second turbine at Riven Hill, in North Nesting, near Laxo.

Advertisement

A third turbine located near Scar Quilse in the North Nesting section of the Viking site will follow shortly.

These are the first of 103 turbines, which will operate in the 4.3 MW power mode, to be fully erected at the wind farm in central Mainland Shetland.

Installation of turbine components got underway in February with over 27 of the tower base sections (pre-installations) erected across site, in addition to the completed turbines.

The completed tip height of the turbine is 155m, which includes the consented hub height of 96.5 metre and blades at 57 metre in length.

Turbine components are being delivered from Lerwick Port under convoy operation and is expected to continue until July.

All turbines are programmed for full erection in 2023, with Viking expected to be fully operational by the autumn of 2024.

Heather Donald, SSE Renewables’ onshore renewables development and construction director said: “The installation of the first turbines at Viking Wind Farm, is not only an exciting step forward in the project, but by reaching this milestone, it underlines our strategy to lead the transition to a net zero future through the world-class development, construction and operation of renewable power assets.

“Seeing the first turbines erected is a testament to everyone involved in the installation process.

“By the end of this year, we expect all of Viking’s turbines to be in place and once operational, in 2024, it will be capable of producing enough energy to power the equivalent of almost half a million homes including every home in Shetland, playing a crucial role in contributing towards the UK and Scotland’s net zero targets.”

Robert Yeates, lead project manager with Vestas, said: “Even with the severe winter weather that delayed our works, we are extremely happy that the overall programme has been kept on schedule and that the first full turbines are now successfully installed.

“This significant milestone has been achieved with the close collaboration with our partner SSE, RJM the principal contractor on the Viking Energy Wind Farm, and our subcontractors.”

Onshore Wind Scotland Shetland SSE Renewables Vestas Viking
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleSkyborn applies to build Swedish offshore project
Next Article Google signs Dutch, Belgium PPAs

Related News

SSE completes 443MW Viking wind farm

August 29, 2024

Viking achieves first power

June 6, 2024

Viking gives Shetland £70m boost

July 21, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}