Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Viking achieves first power
Onshore Wind

Viking achieves first power

SaraBy SaraJune 6, 20242 Mins Read
Viking achieves first power

First power has been produced at the 443MW Viking wind farm on Shetland island, Scotland.

The milestone comes as Shetland gears up to be fully connected to the GB electricity transmission grid for the first time, with the 260 km Shetland High Voltage Direct Current (HVDC) subsea cable project being delivered separately by SSEN Transmission, with energisation expected later this summer.

Advertisement

Engineers will continue to progress through commissioning ahead of the wind farm reaching full power and entering commercial operations later in summer 2024, when it is expected to become the UK’s most productive onshore wind farm.

Construction of the wind farm began in the autumn of 2020 with the last of over 100 turbines being installed at the site in August 2023.

Heather Donald, SSE Renewables’ Onshore Renewables Development and Construction Director, said: “This latest milestone is another step towards cleaner, more secure, homegrown power for Shetland, Scotland and the UK.

“Once again our expert teams have shown what can be achieved in the development, construction and operation of world-class renewable power assets as we look to lead the transition to a net zero future.”

John Scott, SSEN Transmission’s Programme Director, said: “The first flow of power from Shetland to the mainland on the Shetland HVDC link is a key moment for the Shetland community.

“Full energisation, linking Shetland to the GB transmission system for the first time will be crucial in delivering Shetland’s energy security as well as enabling extensive renewable generation development and export.

“A tremendous collective effort from our teams so far, we can now look forward to working through the remaining commissioning phases of the project before it is fully energised later this summer.”

When fully operational, Viking’s 103 Vestas turbines will operate in 4.3MW power mode.

Alongside progress with the Shetland HVDC Link project, work is continuing to connect Shetland’s existing electricity distribution network to the transmission network, connecting Shetland’s homes and businesses to the GB grid for the first time via the new grid supply point (GSP) being constructed at Gremista.

The Kergord-Gremista 132kV overhead lines and underground cable circuits are being installed and are scheduled for completion in 2025.

The HVDC link will then be connected to the new Gremista GSP.

Viking Wind Farm and the Shetland HVDC project are on track for completion in H2.

Onshore Wind SSE Renewables Viking
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleNew US solar additions nudge 12GW in Q1
Next Article AMEA Power closes South African solar financing

Related News

Transformers arrive for Gremista connection project

March 7, 2025

SSE completes 443MW Viking wind farm

August 29, 2024

Ofgem sets £642m allowance for Shetland link

November 30, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}