Vattenfall has completed the monopile installation programme at its Hollandse Kust Zuid offshore wind project in the Dutch North Sea.
All 140 foundations have been completed by contractors Seaway Heavy Lifting & SIF, the developer confirmed.
Advertisement
Siemens Gamesa 11MW turbines are due to be installed at the site.
Vattenfall foundation installation manager Mary Carol Anderson said the milestone marks a “big achievement” for all parties involved in the process.
“Going from installing 34 foundations in the 2021 summer campaign to installing 106 foundation in 2022, is a huge testament to the team,” she added.
Vattenfall said a more detailed assessment of the piling campaign will be published later this month.