Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Jumbo completes Hornsea 2 contract
Offshore Wind

Jumbo completes Hornsea 2 contract

reNEWS EditorialBy reNEWS EditorialNovember 5, 20213 Mins Read
Jumbo to plot Hornsea 2 foundation course

Jumbo has completed the transport and handling of offshore wind turbine foundation components for Orsted’s 1400MW Hornsea 2 offshore wind farm in the UK North Sea.

The Dutch offshore contractor deployed its K-3000 class heavy lift vessel Fairmaster to carry out its scope of transporting 141 monopiles and 131 transition pieces from Rostock, Germany and Aalborg, Denmark to Eemshaven in the Netherlands.

Advertisement

This was the largest amount of monopiles and transition pieces that the company has ever shipped in a single contract as well as the most it has carried with a single heavy lift vessel.

The monopiles themselves were 8.5 to 9.5 metres in diameter and weighed up to 1285 tonnes.

Jumbo’s 152.9 metre long Fairmaster vessel, which has two 1500 tonne cranes, was able to provide a flexible deck layout that assisted in the project’s timing schedule.

Jumbo project manager Maarten De Gruyter said: “This engineered flexible solution made it an extremely efficient vessel for the project and is one of the things we’re most proud of – it helped us conclude the project scope within just 37 voyages in a period of just under twelve months.

“We had close cooperation with DEME Offshore with regards to scheduling, and we could handle many changes to the sailing sequence.

“Ultimately, this meant that we could carry more equipment within less time.

“During the planning phase, we designed and engineered the MP saddles and TP grillages to deliver our proposed vessel efficiency.”

The company said it used inlays in the saddles to accommodate the different diameters of the monopiles and it also installed project-specific lifting lugs on the deck hatches to speed up loading and unloading operations.

As part of reducing the environmental footprint of the construction of the Hornsea Two offshore wind farm, Jumbo was required to include a Green Initiative into its project execution, for which the company chose to sail with biofuel oil from sustainable marine biofuel provider GoodFuels.

Jumbo commercial manager Boudewijn van der Garden said: “We converted the Fairmaster into a kind of ‘Swiss Army knife’ that provided an unrivalled heavy lift vessel intake of large diameter monopiles and transition pieces, but still with the flexibility required for the various lengths and diameters that were to be transported.

“From tender to project conclusion, Jumbo’s focus was to provide a total solution. Our office personnel, engineering teams and vessel crews are now ready for the next challenge.”

Hornsea 2 Jumbo Onshore Wind Orsted
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleCOP26: Chile to increase battery storage to 1.5GWh
Next Article Siemens Gamesa confirms 3.6GW Norfolk order

Related News

Jumbo completes Yunlin TP installation

September 9, 2024

Jumbo completes Yunlin monopile removal job

June 6, 2024

Jumbo extends support on Yunlin

February 15, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Natural Power
    Natural Power
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}