Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Jumbo completes Yunlin monopile removal job
Offshore Wind

Jumbo completes Yunlin monopile removal job

SaraBy SaraJune 6, 20242 Mins Read
Jumbo to install Baltic Eagle TPs

Jumbo Offshore has completed the removal of two monopiles from the Yunlin offshore wind farm off Taiwan.

The Jumbo Offshore crew carried out the work, whilst deploying its DP2 heavy lift crane vessel Fairplayer from Europe to support the onsite operations.

Advertisement

Jumbo Offshore was awarded the contract by Yunneng Wind Power Company (YWPC) earlier this year for the removal of monopiles at the Yunlin site.

The contract award represents an expansion of Jumbo Offshore’s existing scope, involving the transportation and installation (T&I) of the transition pieces.

Under the additional project scope, two monopiles, which previously suffered from a pile run during an earlier project phase, were to be removed.

This involved underwater cutting of the monopiles into sections as well as recovery, transport and offloading of the sections.

The all-encompassing nature of the scope meant working with Jumbo’s dependable subcontractors.

The Fairplayer was outfitted with an underwater abrasive cutting and lifting tool supplied by Claxton Engineering Services, as well as an ROV supplied by IKM subsea and survey equipment by Reach subsea.

With these, the Fairplayer could remove the monopiles successfully. The individual sections were lifted into the vessel’s cargo hold for transportation to a local Taiwanese port and offloading to the quayside.

For the execution of the works, Jumbo Offshore provided a project management team and the engineering construction crew.

From contract signature to successful completion of the works, it took just five months including sailing of the vessel from Europe to Taiwan.

Milad Sheikhi, Head of Sales and Business Acquisition at Jumbo Offshore, said: “Our dedicated team worked solidly to support our client throughout the project and remained flexible.

“Achieving what you set out to accomplish successfully and on time is rewarding for the team.

“Delivering a safe and reliable service as promised is, and always will be our core commitment as a T&I contractor for the installation and decommissioning of future offshore wind projects.”

Jumbo Offshore Wind Yunlin
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article‘Energy transition must accelerate to hit 1.5°C’
Next Article Asian players to power data centres with renewables

Related News

Jumbo completes Yunlin TP installation

September 9, 2024

Jumbo extends support on Yunlin

February 15, 2024

Jumbo joins Yunlin crew

June 12, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}