Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Siemens, NKT, ABB Power Grids win Shetland link contracts
Grid

Siemens, NKT, ABB Power Grids win Shetland link contracts

SaraBy SaraAugust 4, 20203 Mins Read
Siemens

Scottish and Southern Electricity Networks (SSEN) Transmission has appointed the main contractors for the construction of an interconnector linking Shetland and the Scottish mainland.

The four key contractors to install the high voltage direct current (HVDC) link and all associated infrastructure are Hitachi ABB Power Grids, NKT, Siemens and BAM Nutall.

Advertisement

The contract awards follow the recent decision by the energy regulator, Ofgem, to grant final approval for the transmission link, with everything now in place for the start of main construction in late August 2020.

The link, which will connect Shetland to the mainland transmission system for the first time, is required to facilitate the connection of renewable electricity developments on the island.

The project consists of a substation at Kergord on Shetland, which is required for the connection of renewable electricity generators on Shetland. 

These works will be led by Siemens BAM.

The power will then be converted from alternating current to direct current at a HVDC converter station, also at Kergord, before being transported around 270km via underground and subsea cable (257km) to an HVDC switching station at Noss Head, Caithness, in the north of Scotland. 

NKT will be responsible for the manufacture and installation of the subsea cable, with BAM Nuttall delivering all civil engineering works, including the construction of all buildings.

HVDC technology provider Hitachi ABB Power Grids will deliver and commission the HVDC system.

The power will then be transported via the Caithness Moray HVDC link before being converted back to alternating current for onward transmission.

All four contractors played were involved in the construction of the Caithness Moray HVDC link, which has been operational since January 2019.

Enabling works are due to begin at Kergord and Noss Head towards the end of August, with full construction of the AC Substation, and HVDC Convertor and Switching Stations, due to commence in early 2021. 

The subsea cable installation will take place in 2022 and 2023 following its manufacture.

SSEN Transmission director of offshore delivery Sandy Mactaggart said: “The Shetland HVDC link will deliver substantial socio-economic and environmental benefits to Shetland’s, Scotland’s and the UK’s economy, supporting hundreds of skilled jobs in the process as part of the green recovery from the coronavirus pandemic.

“With all major milestones complete, we now look forward to working closely with the Shetland and Caithness communities and other stakeholders throughout the construction and future operation of these critical national infrastructure assets.”

ABB Grid NKT Siemens SSEN Transmission
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleShipping outfit to build turbine installation vessel
Next Article Manor debuts in Taiwan offshore wind market with Yunlin job

Related News

Penultimate cable laying starts at Shetland HVDC interconnector

March 20, 2023

Shetland HVDC link cable laying gets underway

July 8, 2022

Ofgem sets £642m allowance for Shetland link

November 30, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Oceantic Network
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}