ProCon Wind Energy has completed the electrical construction of 35 transition pieces for the 752MW Borssele 1&2 offshore wind project off the Netherlands coast.
The work was carried out at EEW Offshore Structures (Britain) Ltd.
Since June 2019 ProCon has been providing electrical pre-assembly, installation and connection of 35 E-modules and platforms as well as installation of different systems in the transition pieces, including external lighting, navigation, communication and ventilation.
The scope of work also included commissioning and testing of the entire electrical construction of each transition piece.
These tasks have been finished, confirmed ProCon, with only the operations and maintenance manual to produce.
ProCon said it has also continued its cooperation with EEW, starting work on the 30 transition pieces for the Hornsea 2 offshore wind project off the UK coast.
ProCon was awarded the work in September 2019.
In relation to this, EEW Offshore Structures (Britain) Ltd said the first of Hornsea 2’s 400 tonne transition pieces had been upended.