The topside has arrived in Ostend for the offshore substation at the 219MW Northwester 2 offshore wind farm off Belgium.
The journey from Bladt Industries production site in Aalborg, Denmark, took four days, said Parkwind which is part of the consortium building the wind farm.
Advertisement
The port of Ostend will be the temporary home of the 962-tonne structure before installation some 46km from shore.
Bladt is engineering, procurement, construction and installation contractor.
Northwester 2 will feature 23 MHI Vestas V164-9.5MW turbines and is scheduled for completion early next year.