EnBW has completed installation of all 71 Siemens Gamesa 7MW turbines at its 497MW Hohe See wind farm in the German North Sea.
The final unit was put up by Fred Olsen Windcarrier jack-up Blue Tern on Monday, the company said.
Advertisement
Twenty-seven of the 71 Hohe See turbines are already supplying the grid.
The installation outfit will now turn to EnBW’s 112MW Albatros project to erect the same model turbines.
“We have two installation vessels, they will go to Albatros directly and carry on the installation,” EnBW said.
The Hohe See/Albatros complex will feature a total of 87 turbines that provide 609MW of installed capacity.
About 50 ships and more than 600 employees are involved in the construction work which is coordinated by the EnBW offshore subsidiary in Hamburg.