Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Wires rolling for Triton onshore grid
Offshore Wind

Wires rolling for Triton onshore grid

Robin LancasterBy Robin LancasterMarch 22, 20191 Min Read
Wires rolling for Triton onshore grid

Cables for the onshore network at Innogy’s 857MW Triton Knoll offshore wind farm off Lincolnshire in east England have started rolling off the production line.

The Nexans-made HVAC cables are being delivered to the Port of Boston on 28 cable drums, which are typically 4.5 metres by 3.5 metres in size. The majority are set to arrive on Sunday 24 March, Innogy said.

Advertisement

The cable drums will then be transported on heavy goods vehicles, via the A16 to a secure storage compound near to the project’s cable route.

Deliveries will start from 7.30am on 25 March until 27 March, and will be staggered to help minimise effects on the road network.

Innogy said each cable drum weighs between 17 to 26 tonnes and contains between 1023 metres to 1690 metres of cable.

In total, 306 drums will be required for the entire Triton Knoll onshore cable route, adding up to more than 360km of cable.

Innogy said the milestone marks the delivery of the “first major elements of the project’s onshore electrical system, and will be ready for installation along the cable route in summer 2019”.

Offshore Wind Solar Triton Knoll
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleOsprey swoops for Albatros topside delivery
Next Article Siemens Gamesa, Van Oord confirm Fryslan feast

Related News

Partrac buoys demark Triton Knoll site

October 17, 2019

Triton kicks off onshore

September 11, 2018

Triton nails financial close

August 31, 2018
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Oceantic Network
  • LSP
    LSP Renewables
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}