VBMS has signed a preferred supplier and early works agreement to deliver and install export and array cables at Innogy’s 860MW Triton Knoll offshore wind farm in the UK North Sea.
The work will be carried out in consortium with NKT Cables and will involve installation of two 50km export links and 97 66kV array wires.
VBMS will use two of its cable lay vessels for the work, which is scheduled to take place in 2020.
The contract is valued at €80m and is subject to financial close, which is expected in the second quarter of 2018, the company said.