The first turbine components will arrive on 29 September at Banks Renewables’ four-turbine Lambs Hill wind farm near Stockton-on-Tees.
Deliveries are scheduled to continue until mid-October.
Erection work on the first turbine is scheduled for 4 October, with commissioning of the finished project due to take place by the end of the year.
The civil contractor on the 8MW project featuring Senvion MM100 turbines is Bury’s Cheetham Hill Construction.