Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » BOEM delays Vineyard approval
Offshore Wind

BOEM delays Vineyard approval

SaraBy SaraAugust 12, 20192 Mins Read
Safety first for small vessels

The US Department of Interior’s Bureau of Ocean and Energy Management (BOEM) is delaying the approval of the Federal Environmental Impact Statement (FEIS) for the 800MW Vineyard Wind project off the coast of Massachusetts.

BOEM wants to conduct a supplemental study.

Advertisement

A statement from the project developer, Vineyard Wind LLC, said the federal government’s decision comes “as a surprise and disappointment”.

The statement added: “To be clear, the Vineyard Wind 1 project remains viable and is committed to move forward.

“While we appreciate that the discussion on cumulative impacts is driven by rapid growth of the industry beyond our project, we urge the federal government to complete the review of Vineyard Wind 1 as quickly as possible.”

Despite the delay, the developer said it remains “deeply committed” to the emerging industry’s success.

“We firmly believe that once regulators are fully satisfied, our project and dozens of others will deliver billions of dollars of new investment in ports, enhanced energy independence, and above all, high-paying, long-term jobs for thousands of Americans,” the statement said.

Business Network for Offshore Wind chief executive Liz Burdock said the decision to delay the approval of the FEIS for the project and expand the environmental review is “a step in the wrong direction”.

Burdock added that the ruling also contradicts the Trump administration’s objective of reducing regulatory constraints on business growth.

She said: “Requiring a project to assess the impacts of all potential future projects, even though those future projects are not yet defined, is extraordinary.

“This requirement adds cumbersome regulatory hurdles to an already long and arduous process – a process that the industry has thus far responded to with rigor, showing that this form of energy production is safe, protective of the environment, stimulating to the economy, and in keeping with the needs of all commercial interests.”

The Offshore Wind Business Network encouraged BOEM to provide a ruling that follows the original timeline agreed to with the Vineyard project.

BOEM Massachusetts Offshore Wind Vineyard Wind
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleGreen Investment Group swoops for 40% of EA1
Next Article Vattenfall commits to Dutch hybrid play

Related News

Presidential hopeful urges swift Vineyard EIS review

August 15, 2019

Vineyard calls for environmental report release

July 18, 2019

Vineyard passes muster with Massachusetts

February 5, 2019
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}