Seaway Offshore Cables has completed array cable installation at SSE’s 588MW Beatrice wind farm off Scotland.
The Subsea 7 Renewables & Heavy Lifting-owned unit put in place 91 JDR-supplied wires to connect all 84 turbines locations and two offshore transformer modules.
SSE said the milestone means all offshore cabling for the wind farm is now completed.
Swire Blue Ocean jack-up Pacific Orca remains on turbine installation duty and is putting in Siemens Gamesa 7MW units in the Moray Firth.
The wind farm, which has already notched first power, is expected online next year.
Copenhagen Infrastructure Partners and Red Rock Power are shareholders in the project alongside SSE.
Image: BOWL