Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Corio-Total get green light for 1.5GW Outer Dowsing
Offshore Wind

Corio-Total get green light for 1.5GW Outer Dowsing

Paul StephenBy Paul StephenFebruary 10, 20262 Mins Read
Wind sets new UK record

UK Energy Secretary Ed Miliband has granted planning consent to Corio and TotalEnergies’ 1.5GW Outer Dowsing wind farm off east England.

A final determination had initially been due by 10 October 2025 after the Planning Inspectorate completed a six-month examination of the 100-turbine project’s DCO application last April.

Advertisement

However, the deadline was subsequently postponed until today (10 February) to allow officials sufficient time to request and consult on further information.

Outer Dowsing Project Director David Few said: “This is great news for the project and for the country, as it means Outer Dowsing is one step closer to building enough UK-generated power to supply 1.6 million homes using the renewable energy of the wind.

“We would like to thank all those who have contributed to the project so far. Together, our efforts are making a major contribution to the UK Government’s clean power ambitions and our future energy security.”

Nicolas Payer, Country Chair for TotalEnergies UK, added: “TotalEnergies is delighted that the Outer Dowsing project has reached this important milestone. TotalEnergies has been a long-term investor in this project, which will make a significant contribution to providing low-carbon power to homes and businesses across the UK.”

Corio Generation Head of Europe Sharn Warn said: “The consent award for Outer Dowsing comes after four years of hard work by some of the most talented individuals in the industry and is a testament to the thorough and diligent approach undertaken by the project team.”

The Round 4 project is due to connect in November 2030 to a new National Grid substation at Weston Marsh in Lincolnshire that will feed into existing overhead lines.

Export cables will make landfall at Wolla Bank and run via an onshore substation at Surfleet Marsh.

Evidence heard during the DCO examination included representations from Orsted and Equinor on mitigation for projected wake effects at neighbouring wind farms operated by the duo.

The Outer Dowsing developers also proposed seasonal restrictions on construction and various other design changes to address environmental concerns raised by statutory consultees including Natural England.

The project did not secure a Contracts for Difference in January’s Allocation Round 7 and will be eligible to bid in AR8.

A three-year build-out is scheduled to start in 2027.

The project is expected to create £2bn of UK investment in its lifetime and 1,000 UK-based jobs during construction.

consent Corio DCO DESNZ Ed Miliband Offshore Wind Outer Dowsing TotalEnergies
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleNordseecluster substations completed in France
Next Article Losses narrow at Siemens Gamesa

Related News

UK delays Outer Dowsing permit decision

October 6, 2025

JERA Nex BP, EnBW get green light for Morgan

August 29, 2025

Corio seeks permit for Sceirde Rocks

January 16, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • LSP
    LSP Renewables
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}