EEW SPC has delivered the first set of monopiles for RWE’s 1100MW Thor offshore wind project in Danish waters.
In March EEW SPC completed delivery of the first of twelve shipments for the array at the port of Rostock.
Advertisement
Fifteen out of a total of 36 monopiles EEW SPC is producing for the project have been collected, the company said.
The remaining shipments are scheduled to take place between now and July.
The monopiles are an average 82 metres in length, and weigh some 1,300 tonnes each.
The Thor wind farm is located approximately 22 kilometers off the west coast of Jutland and is scheduled to become fully operational in 2027