Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Elia postpones Princess Elizabeth contracts
Offshore Wind

Elia postpones Princess Elizabeth contracts

Eleanore RobinsonBy Eleanore RobinsonFebruary 5, 20253 Mins Read
Elia postpones Princess Elizabeth contracts

Elia Transmission Belgium (ETB) has announced it is temporarily postponing the signing of the final contracts for Princess Elisabeth Island due to the price increase for high-voltage direct current (HVDC) infrastructure.

Postponing the signing of the contracts is not without consequences but provides extra time to weigh the current design against alternative concepts in the changing market context, according to the company.

Advertisement

These alternatives are also feasible but require a joint action plan with all the parties involved, as there are currently too many uncertainties both in policy and regulation, it added.

Given the strategic importance of the Belgian energy island and its crucial role in the country’s electricity supply in the coming decades, Elia said it wishes to keep all options open by postponing the signing.

Meanwhile, the construction of the artificial island (foundations) and the implementation of the already-signed alternating current (HVAC) contracts remain on track.

This ensures the realisation of two (700MW + 1400MW) of the three future offshore wind farms, meaning 60% of the new Princess Elisabeth wind zone is already being implemented, Elia said. 

To connect the third wind farm (1,400MW), Elia is currently negotiating for two HVDC converters (one on the island and one on the Belgian coast).

These converters must, in addition to connecting this wind farm, also enable the development of a hybrid interconnector to the UK (Nautilus project).

The international tender that Elia has set up for these direct current components shows an overheated supply chain with significant price increases, the company reported.

Although the terms from the supplier involved are comparable to those of other European grid operators, they are – despite its efforts – much higher than our initial estimates, Elia said. 

This significant cost increase – specific to HVDC – is due to scarcity, combined with the rise in material costs and inflation.

To realise the HVDC contracts within the set timeframe (by 2032), the chosen supplier has given us a deadline to award the proposed contract by mid-February 2025 at the latest.

The company said: “Since Elia, as a grid operator, implements decided policies, it seems inappropriate to us, in the current exceptional market conditions, to make a unilateral decision without further political support.

“To keep all options open, Elia has analysed various alternatives over the past few weeks, weighing the pros and cons and taking a range of uncertainties into account.

“These are complex analyses that require considerable expertise and are currently being discussed calmly with all stakeholders.”

As Elia will not be awarding the negotiated HVDC contract in February 2025, the HVDC converters will not be built to the original schedule, the developer said. 

It will be up to the government to confirm or revise the reference concept, it added.

Elia said: “This is a strategic decision regarding Belgium’s electricity supply for the coming decades. If the reference concept is chosen, the construction of the HVDC converters will be postponed to a date to be determined with the equipment manufacturers.

“The project’s overall lead time is estimated at around three years.”

Belgium Elia HVDC Nautilus Offshore Wind Princess Elisabeth
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleStatkraft gets nod for UK PV project
Next Article Macquarie gives Greenalia €97m loan

Related News

Work starts on Belgium energy island

April 30, 2025

Elia secures €650m from EIB for energy island

October 28, 2024

Plans unveiled for ‘first artificial energy island’

October 5, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Ørsted
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}