Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Plans unveiled for ‘first artificial energy island’
Grid

Plans unveiled for ‘first artificial energy island’

Eleanore RobinsonBy Eleanore RobinsonOctober 5, 20223 Mins Read
Plans unveiled for 'first artificial energy island'

Belgium transmission operator Elia has presented its draft plans for what will be the world’s first artificial energy island.

The Princess Elisabeth Island will be located almost 45 km off the Belgian coast and will serve as the link between the offshore wind farms in the second offshore wind zone (which will have a maximum capacity of 3.5GW) and its onshore high-voltage grid.

Advertisement

The energy island will also be the first building block of a European offshore electricity grid that will serve as a central hub for new interconnectors with the UK and Denmark.

Belgium’s Maritime Spatial Plan (2020-2026) provides for the development of a new wind power production zone in the Belgian part of the North Sea: the Princess Elisabeth zone.

In line with the Belgian Electricity Act, Elia is responsible for extending the transmission grid based on plans that must be approved by appropriate ministers.

The draft plans for the first energy island are now ready and the tender process is being prepared.

The Princess Elisabeth Island will combine both direct current (HVDC) and alternating current (HVAC).

The island’s high-voltage infrastructure will bundle the wind farm export cables from the Princess Elisabeth zone together, while also serving as a hub for future interconnectors with the UK (Nautilus) and/or Denmark (TritonLink).

These will be hybrid interconnectors that have a dual function and will therefore be more efficient.

They will ensure the exchange of electricity between countries and will also be connected to gigantic offshore wind farms in the North Sea that will provide our country with large volumes of renewable energy.

The energy island will be located almost 45 kilometres off the coast and will occupy an area of approximately five hectares above the waterline.

The artificial island will be constructed in the Princess Elisabeth wind zone and will be constructed from concrete caissons filled with sand.

The island will mainly house transmission infrastructure that will be linked to new wind farms and will form part of connections to future interconnectors.

A small harbour and helicopter pad are also due to be built for maintenance teams.

In order to connect all future offshore installations to the Belgian high-voltage grid, 300 km of alternating current cables and 60 km of direct current cables will be needed.

The energy island will rely on support from Belgium’s post-COVID-19 recovery plan, which Belgium asked the European Commission to approve, meaning it is due to receive a subsidy of around €100m.

The tender process for the island is being prepared, as is the development of the environmental impact assessment, the preparation of the permitting procedure and the application for a concession of public space.

The construction of the island is due to start in 2024 and the island should be completed in mid-2026.

From then on, the construction of the electrical infrastructure on the energy island will start.

The construction of future wind farms is being organised by the Government through a series of tenders.

The connection of the wind farms to the Elia grid is linked to the commissioning of two onshore grid reinforcement projects: the Ventilus and Boucle du Hainaut.

Elia aims to achieve full connection capacity by 2030.

Elia Group chief executive Chris Peeters said: “The Princess Elisabeth Island constitutes a big leap forward for the energy transition.

“In addition to bringing 3.5GW of additional offshore wind energy to shore, the island will also be the first link in a European offshore electricity grid.

“It will allow us to access the huge offshore wind potential that the North Sea still has to offer us.”

Belgium Elia Grid Offshore Wind
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleFirst Solar sells Japanese O&M platform
Next Article Siemens Gamesa onshore chief leaves turbine firm

Related News

Work starts on Belgium energy island

April 30, 2025

Elia secures €650m from EIB for energy island

October 28, 2024

DEME, Jan De Nul to build Belgian energy island

February 28, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Ørsted
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}