Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Hunterston inks deal for subsea cable production factories
Offshore Wind

Hunterston inks deal for subsea cable production factories

reNEWS EditorialBy reNEWS EditorialAugust 25, 20214 Mins Read
Peel Ports unveils Hunterston vision

Hunterston Port in Ayrshire has signed an option agreement with a sustainable energy sector company for the construction of two cable factories for use by the offshore wind industry. 

Owner Peel Ports Clydeport is primed to secure the deal with XLCC for a 70-acre facility producing state-of-the-art high voltage direct current (HVDC) cable for use in the subsea transmission of renewable energy.

Advertisement

The plan, expected to create 900 permanent jobs, also includes the construction of research and development laboratories, offices, stores, electrical infrastructure and a high-tech cable delivery system, taking over almost a quarter of the land available for development at the former ore and coal terminal.

The development requires investment in the order of £370m (€432.5m) for buildings and plant, with another £200m for a commissioned specialist ship capable of transporting the massively heavy cable reels.

The vessel would be shared with a third XLCC factory planned for Wales.

XLCC has instigated the planning process with North Ayrshire Council and a planning application is expected to go before committee in February next year.

If consent is given work would begin in April, with another 400 jobs created during the construction phase.

It comes a year after Peel Ports announced it was seeking between £10m and £30m from an investment partner to develop infrastructure to support floating wind construction and oil sector asset decommissioning and recycling at Hunterston Port.

The schedule is for test lengths of cable to be made by April 2023, with 200 jobs in place at the start of that year.

Full manufacturing production will be underway by November 2024 with the remaining 700 jobs in place between May 2024 and November 2024. 

 A three week online public consultation on the plans began yesterday (August 23).

Peel Ports Clydeport director Jim McSporran said: “We are very excited by the signing of this option, which if realised would result in many hundreds of high-quality jobs in one of Scotland’s highest unemployment areas.

“Our vision for Hunterston PARC, launched last year, was for the redevelopment of 300 acres to create a nationally significant energy and marine campus, bringing together leading industry operators, world-class universities and the latest innovators, and to deliver technological advances in areas such as power generation and aquaculture.

“The technology which is to be developed by XLCC would be a game changer for deep sea renewable energy transmission and certainly falls into our vision remit.

“While the scope of the development would give us an anchor tenant, we are also close to other major deals currently under non-disclosure agreements.

“Hunterston is a site with a level of infrastructure assets unique to the UK and possibly Europe, and we believe its time has come.”

XLCC director Alan Mathers said: “We chose Hunterston because of our requirement for a deep water jetty able to cope with the huge size of ship needed to transport our cable reels, for its large land space available very close to this jetty and because Hunterston is already designated as a Port and Energy Hub in local and Scotland’s national plans.

“But just as important is the fact that the talent we need is available locally, with Hunterston B’s closure in 2023 providing access to people with the sort of transferable skills we will need.

“While we envisage Hunterston as a high voltage cable production plant, we also plan a research and development facility which will be a global game changer in technological development of stronger, lighter and more durable cable that will allow its use in deeper water than is now possible.

“We are hopeful of achieving planning consent from North Ayrshire Council early next year, and if we do this development will happen.”

Mathers added that discussions were underway with UK Steel, and that domestic steel would be used in the cables wherever possible.

He said UK Steel had told him XLCC’s optimum production levels would protect up to 1000 UK jobs.

XLCC production will be for the interconnector and offshore wind farm export cable market.

These cables would be used to carry supply to the National Grid where it will flow to consumers across the country, moving the UK closer to having a zero-carbon, low-cost energy network.

XLCC is in discussions with three offshore energy companies about the supply of cable which would be produced at Hunterston, with delivery from 2025.  

Export cable Hunterston Offshore Wind Scotland
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleMarmen Welcon, Smulders forge US TP alliance
Next Article RWE seeks offshore know-how for Sofia build

Related News

UKIB invests £20m in Scottish cable factory

September 26, 2024

Scots HVDC cable factory gets planning nod

June 30, 2022

Mainstream secures land to support Scottish offshore plans

November 22, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}