German offshore wind farm Nordsee One is tendering for the exchange of major components on 47 wind turbines.
The contract starts on 1 March 2022 until the last MCR is completed.
The main tasks of the scope will be the replacement of major components, such as rotor shaft-bearings, documentation and reporting of the tasks.
It will also include all tasks which are necessary to keep the the turbines running safe and sustainable, full logistics (including provision of heavy lift vessels) and base infrastructure.
Commissioned in 2017, the 332MW project is located in the German Bight, approximately 32 km north of the Island Juist.
The water depth ranges roughly between 26 metres and 34 metres with 2.7 m tidal range.
Under operation are 54 Senvion 6.2M126 turbines with a nominal output of 6.15MW.
Interested parties have until 11am on 5 July to submit a bid.