Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » TECO to deliver 1GW Hai Long substation
Offshore Wind

TECO to deliver 1GW Hai Long substation

SaraBy SaraSeptember 30, 20212 Mins Read
TECO to deliver 1GW Hai Long substation

Hai Long Offshore Wind Project and TECO Electric & Machinery Co have signed a preferred supplier agreement for a 1044MW onshore substation in Taiwan.

The onshore substation will transmit the power output from Hai Long 2a (300MW), 2b (232MW) and Hai Long 3 (512MW) to Taiwan Power Company’s substation to connect to the grid.

Advertisement

The process of grid connecting the three wind farms is expected to commence in 2024.

TECO will act as engineering, procurement and construction (EPC) contractor to deliver the onshore substation, including the civil and electromechanical engineering, procurement, construction and commissioning for all aspects of the asset.

Hai Long and TECO will also work together with Tier 1 and 2 suppliers and procure main power equipment from local manufacturers to fully support the goal of localisation of the offshore wind industry in Taiwan.

Hai Long 2 and 3 wind farms are located 40-50 km off the coast of Changhua.

The developer said it has gone beyond the government’s localisation requirements, by contracting TECO, a local Taiwanese company, as EPC contractor for the onshore substation not only for Hai Long 2a, but also for Hai Long 2b and Hai Long 3, which do not have any localisation obligations.

Hai Long project director Felipe Montero said TECO has a “wealth of experience” in electromechanical engineering, power equipment and the construction of onshore substations for offshore wind, which makes it the “ideal local partner” for the construction of Hai Long’s onshore substation.

TECO president George Lien said that TECO has been awarded EPC contracts for onshore substations for Taiwanese offshore wind farms for three consecutive years, with a total of around 2GW of onshore substations installed.

Hai Long Offshore Wind TECO
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleSingapore crew completes Changhua 1&2a substations
Next Article Nordex wins 50MW Dutch wind order from Shell

Related News

Hai Long awards pin piles fabrication contract

October 12, 2022

Hai Long 2 chooses foundations supplier

March 30, 2022

Siemens Gamesa completes Hai Long hat-trick

May 5, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}