Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » TenneT topside heads for Hollandse Kust
Offshore Wind

TenneT topside heads for Hollandse Kust

reNEWS EditorialBy reNEWS EditorialSeptember 4, 20232 Mins Read
TenneT topside heads for Hollandse Kust

The topside for TenneT’s Dutch offshore platform Hollandse Kust (west Alpha) is set to leave Belgium’s Port of Antwerp for its final destination 50km off the coast of Egmond aan Zee.

Measuring 47 metres long, 35 metres wide and 25 metres high, the large steel box weighing over 3600 tonnes is ready to be placed on the jacket at sea after being successfully placed on a floating pontoon.

Advertisement

This foundation was been firmly anchored to the seabed last year. Almost two years after the first steel cut, this is the second topside built for TenneT by the Equans/Smulders combination.

“First, the floating pontoon is towed to the port of IJmuiden,” said construction manager on behalf of TenneT Matthijs Knollenburg.

“As soon as all weather conditions give the green light for the installation on the jacket, the pontoon will sail to its final destination at sea.

“At that time, the crane vessel Thialf of Heerema Marine Contractors is also on its way from the Norwegian port of Stavanger to that location.”

As soon as the two vessels meet at sea, the pontoon moors against the Thialf.

“The topside is then ‘loosened’, after which the crane vessel lifts the construction into the air,” said Knollenburg.

“Once the pontoon has been towed away, the Thialf will sail for another 500 metres towards the jacket. So-called cones are attached to the jacket.

You can compare this with inverted ice cream cones with which you can lower the topside exactly in the right place without too much measuring.”

After installation, a hotel barge is placed next to the platform so the Equans team can start the welding work to fix the topside. Earlier this year, the two sea cables, with which the green electricity from the wind farm will soon come ashore, were installed by Jan de Nul Group.

 The ‘socket at sea’ will be ready for commissioning before the end of this year.

In 2025, Ecowende (a joint venture of Shell and Eneco) will place the 54 wind turbines in the offshore wind farm and connect them to TenneT’s ‘socket’. With an installed capacity of approximately 760MW, Ecowende can green approximately 3% of the current Dutch electricity demand.

The wind farm is scheduled to be commissioned in 2026.

Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleKelag opens 26MW Austrian wind farm
Next Article Cable laying begins at UK’s 1.4GW Sofia

Related News

Hollandse Kust topside set for North Sea voyage

May 14, 2025

TenneT topside in place at Hollandse Kust

September 8, 2023

TenneT installs HKN transformer station topside

October 5, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}