Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » EBRD mulls backing 1.1GW Egyptian array
Onshore Wind

EBRD mulls backing 1.1GW Egyptian array

SaraBy SaraNovember 7, 20243 Mins Read
EBRD mulls loan for 1.1GW Egyptian project

The European Bank of Reconstruction and Development (EBRD) is considering lending up to $200m for a 1100MW wind project in Egypt.

EBRD is looking to lend senior debt financing on a project finance basis of up to $200m in favour of Suez Wind Energy SAE, a special purpose vehicle incorporated in Egypt for the purpose of constructing and operating the wind farm in the Gulf of Suez region.

Advertisement

The scheme requires a total investment of $1bn.  

Suez Wind Energy will be established and owned by a consortium of sponsors that includes ACWA Power (ACWA) and Hassan Allam Utilities (HAU) Energy.

ACWA Power is an experienced international developer of power generation, desalinated water and green hydrogen production projects.

HAU Energy is a newly established renewables equity platform that will be ultimately owned by Meridiam (45%), HAU (30%) and EBRD (25%).

The project involves the development of the wind farm on two plots of land in the Gulf of Suez (GoS). 

The GoS is located on a globally important bird migration flyway at the Rift Valley in the Red Sea, where concentrations of 13 migratory avian species pass through the area during the spring and autumn each year and this may present a significant collision risk to birdlife.

This danger is compounded through existing as well as planned wind farms in the wider area as well as associated overhead transmission lines.

The southern plot is located within the Gebel El Zeit Important Bird Area (IBA) which has also been designated as Critical Habitat (CH) as per EBRD’s E&S Policy. 

The IBA is an important corridor for migrating birds.

The ESP sets out strict requirements for the development of projects in CH, including the need for net gain of those biodiversity features that trigger CH designation, in this case various species of migrating birds. 

The northern plot is located outside of the IBA and is not CH, nevertheless bird migration over the plot is significant and the project will need to ensure no net loss of biodiversity.

Environmental and social impact assessments have been conducted for both plots in line with EBRD’s ESP requirements and consider all relevant impacts and risks, with an emphasis on migrating birds. 

Two years of bird surveys have informed an assessment of impacts to birds supported by collision risk modelling and consideration of implementation of a regional Active Turbine Management Programme, which involves radar assisted turbine shut down on demand and which applies to all wind power projects in the GoS and will apply to the project.

ACWA Power EBRD Onshore Wind
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleDong Fang bags SOV contract from Vestas
Next Article SSE achieves first power at debut EU wind site

Related News

AI bird wind farm tracker proves effective

April 25, 2025

ACWA achieves FID on 1.1GW Suez wind project

January 2, 2025

‘Localising GO market boosts renewables investment’

December 2, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}