EnBW has started construction of the 21MW Steinheim wind farm in Germany.
Steinheim will comprise five Vestas V150-4.2MW turbines with 166-metre hub heights.
Advertisement
EnBW said road construction and laying of the cables started in early April.
Foundation work will follow from May to June.
Turbines are due to be delivered and installed from August.
The planned commissioning is in December 2022, EnBW said.
Areas that are only temporarily required for the construction will be restored to their original condition in 2023, it added.