Vestas has received a firm order from UAB Vejoteka, owned by Enefit Green, for the Kelme 2 wind farm project in Lithuania.
The order consists of 14 V162-6.2MW wind turbines and includes supply, delivery, and commissioning of the turbines.
Upon completion, Vestas will service the turbines under a 35-years Active Output Management 5000 (AOM 5000) service agreement designed to ensure optimised performance of the assets.
Turbine delivery is expected to begin in the first quarter of 2025 with commissioning scheduled for completion in the third quarter of 2025.
“I am pleased that our collaboration with Enefit Green across the Baltic states continues and is now spanning from Estonia to Lithuania,” states Jens Pinderup, Vice-president of Sales East at Vestas.
“The entire area offers huge potential for wind energy projects, and we are proud that our EnVentus wind turbines offers a competitive solution for our customers while helping to decarbonise the energy system in the Baltic region.”