Vestas has secured three orders totalling 191MW across Germany and Poland as part of its fourth-quarter intake.
The company said Uhl Windkraft has ordered 11 V172-7.2MW turbines for the 79MW Schnabelwaid project in Germany.
According to Vestas, delivery is planned to begin in the first quarter of 2027 with commissioning scheduled to start in the third quarter of 2027.
Wpd GmbH has placed an 80MW repowering order for the Reinstedt project in Germany using 11 V162-6.2MW turbines and two V150-6.0MW machines.
Commissioning for Reinstedt is due to begin in the fourth quarter of 2026 after deliveries start in the second quarter of that year.
In Poland, FW LUBIEŃ 1 SP. Z o.o. and Greenvolt Power Group Sp. z o.o. have ordered eight V150-4.0MW turbines for the 32MW Lubień project.
Vestas added that deliveries for Lubień are planned to start in the first quarter of 2027 with commissioning from the second quarter of 2027.