Vestas has received a firm order from Thyboron-Harboore Vindmollelaug for a 15MW wind turbine to be installed directly on the waterfront in the Port of Thyboron in northwest Denmark.
The order consists of one V236-15.0 MW wind turbine and includes supply, delivery, and commissioning of the turbine.
The order also includes a 20-year AOM4000 service agreement as well as an agreement for Vestas to do test and verification activities on the turbine.
Turbine delivery is planned to begin in the first quarter of 2024 with commissioning scheduled for completion in the second quarter of 2024.
Vestas has already installed the prototype of the turbine at the Osterild National test centre in Denmark and received firm orders for units for offshore projects in Germany, Poland, and the Netherlands, and will start installing the first turbines offshore from 2025.
“We are very pleased to install the new V236-15.0 MW turbine at a site in Thyborøn that offers great wind conditions for optimal energy production. Nearly 2800 local shareholders have financed the turbine, and we look forward to showcase it to locals and tourists as we expect it to become an attraction,” says Jens Jorgen Birch, spokesperson at Thyboron-Harboore Vindmollelaug.