Vestas has secured three orders in Finland totalling 277MW for EnVentus turbines across the Kannisto, Korkeamaa and Salo-Ylikoski projects.
Vestas said the 124MW Kannisto project will use 20 V162-6.2MW turbines with delivery planned to begin in Q2 2027 and commissioning scheduled to begin in Q3 2027.
Advertisement
The company added that the 108MW Korkeamaa project will comprise 15 V162-6.4MW turbines and two V162-6.2MW units, with delivery and commissioning planned to begin in Q2 2027.
The 45MW Salo-Ylikoski project will use seven V162-6.4MW turbines under a 25-year AOM 5000 Service Agreement, according to Vestas.
Each project includes a 25-year AOM 5000 Service Agreement.