Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Transformers arrive for Gremista connection project
Grid

Transformers arrive for Gremista connection project

reNEWS EditorialBy reNEWS EditorialMarch 7, 20253 Mins Read
Transformers arrive for Gremista connection project

SSEN Transmission’s work to connect Shetland’s local electricity network to the national grid has reached a milestone with the arrival of two new transformers – the largest components in the project.

The transformers (pictured), each weighing around 59 tonnes, are key electrical components in the ongoing Gremista electricity connection project.

Advertisement

Once fully installed, the transformers will ensure the site’s ability to handle current and future electricity demand, helping to enable and manage the flow of energy through the substation and improving the network’s reliability and efficiency.

The two units arrived in Lerwick Harbour’s Greenhead Base before being loaded onto a multi-axle vehicle by specialist haulier RRS.

They were then transported to their final location at the new Gremista Grid Supply Point (GSP).

The transformers travelled in convoy from the harbour to the substation at a reduced speed due to their size and to ensure their safe delivery.

Deputy project director for SSEN Transmission Mark Kelly said: “The arrival of these transformers is a significant step forwards in our new Gremista Grid Supply Point and wider Gremista Connection project, which will strengthen the energy infrastructure here in Shetland.

“Once this link is complete, it will form the crucial land connection between the Shetland HVDC Link to the GB mainland and the local Shetland grid supply point here at Gremista, connecting Shetland to the GB energy system for the first time. 

“This will enable the supply of clean power to homes and businesses, including at times when local generation on Shetland’s electricity distribution network does not meet demand.

“While the journey between the harbour and the final location for the transformers was relatively short, we worked closely with our contractor Morgan Sindall Infrastructure to carefully plan for their safe arrival to Gremista with minimum disruption.

“We thank the local community for their continued patience while we work to complete this project and will keep them informed as this project progresses.”

Morgan Sindall Infrastructure’s managing director for energy Peter Kirk said: “These transformers will enable local renewable energy to flow to the islands’ homes and businesses by connecting people, places and communities through innovative and responsible infrastructure.”

SSEN Transmission’s Gremista to Kergord connection project involves creating a 22km connection between the new Gremista GSP and the Kergord Substation, which was completed in 2024 as part of the Shetland HVDC link, using a combination of overhead line and underground cabling.

Once complete, the Kergord-Gremista link will provide a connection to Shetland’s local electricity distribution network, connecting the islands to the GB energy system for the first time and helping to secure Shetland’s future electricity supply.

The Kergord-Gremista link is expected to be completed by the end of 2025.

Gremista Grid Morgan Sindall Infrastructure Shetland SSEN Transmission Transmission
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleWomen in Renewables event champions industry’s talent
Next Article RES ‘disappointed’ as Scots wind farm refused

Related News

Viking achieves first power

June 6, 2024

Landslide stops work at SSEN’s Shetland grid project

May 8, 2024

Penultimate cable laying starts at Shetland HVDC interconnector

March 20, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • TGS
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}