Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » SSE’s first battery goes online
Energy Storage

SSE’s first battery goes online

reNEWS EditorialBy reNEWS EditorialApril 12, 20243 Mins Read
SSE's first battery goes online

SSE Renewables’ first battery energy storage system (BESS) project at Salisbury in Wiltshire, England is now fully operational.

The 50MW/100MWh storage project, which could power over 80,000 homes for two hours at times of peak demand, is the first operational battery site in SSE’s portfolio.

Advertisement

The asset is now trading in Britain’s wholesale energy market following the completion last week of final energisation tests at the site. Battery storage plays a key role in unlocking the path to net zero because of its ability to hold and release energy when most needed, said the developer.

The Member of Parliament for Salisbury John Glen, who also serves as Paymaster General and Minister for the Cabinet Office, officially marked the asset going operational at a ceremony held today.

Construction of the 26-battery unit project began on a site next to the old Quidhampton Quarry at Salisbury in 2022 in conjunction with project partners, technology group Wärtsilä.

The BESS is capable of storing up to 100MWh of energy for flexible dispatch when needed to the National Grid. When called upon, the system can operate for up to two hours at a time at times of peak demand.

 “I am delighted to formally open Salisbury’s battery storage site,” said Glen (pictured left with SSE Renewables solar & battery head of construction Alun Robinson).

“SSE Renewables have installed 26 batteries on this site and they are now fully operational.

“This welcome investment means supply of energy from renewable sources is reliable. Salisbury is leading the way as we continue our journey to net zero.”

SSE said Salisbury BESS is now the company’s flagship operational battery site and will make an important contribution to the delivery of its Net Zero Acceleration Programme, a fully funded five-year investment plan which will see it investing over £7bn to 2027, or almost £4m a day on average, to deliver the low carbon infrastructure that will support the transition to net zero, including new battery storage technology.

In addition to Salisbury, SSE is constructing a 150MW battery project in Ferrybridge, West Yorkshire, which is due to complete in the first half of next year, and a 320MW battery project in Monk Fryston, North Yorkshire.

“It is with great pride that our first battery storage project at Salisbury is now fully operational, a huge milestone for everybody at SSE Renewables,” said director of development and construction – solar & battery Richard Cave-Bigley.

“Being a first-of-a-kind project for SSE, the project team has done a tremendous job throughout construction, and I’d like to congratulate everybody involved for their efforts to get to this stage, and I’d like to thank our project partners, Wärtsilä, for their work.

“Salisbury BESS will be a fantastic asset for SSE Renewables and our growing operational portfolio.”

Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleEcowende goes silent on HKW6 monopiles
Next Article Stuart resigns as UK Energy Minister

Related News

SSE’s first BESS project reaches milestone

October 18, 2023

SSE takes FID on UK 150MW battery project

May 12, 2023

SSE forms renewables dream team

November 14, 2018
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Ørsted
  • Oceantic Network
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}