Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Approval for Scottish 275kV upgrade project
Grid

Approval for Scottish 275kV upgrade project

Eleanore RobinsonBy Eleanore RobinsonAugust 21, 20243 Mins Read
SSEN selects preferred bidders for UK grid project

SSEN Transmission has welcomed the decision by Scottish Ministers to grant consent for the Creag Dhubh-Dalmally 275kV overhead line.

The project is part of a wider strategy to upgrade the capacity of the main electricity transmission network across Argyll and Kintyre from 132kV to 275kV, which is essential to enable the growth in renewable energy across the region. 

Advertisement

The Argyll and Kintyre 275kV Strategy is also a key component of SSEN Transmission’s Pathway to 2030 programme, a £20bn investment that will support thousands of jobs and provide a major boost to local and national economies.

This backing represent a major upgrade of the electricity transmission network across the north of Scotland to enable the connection and transportation of homegrown renewable energy to demand centres across the country.

They are also part of a GB-wide renewal of the transmission network that is required to meet UK and Scottish government clean power and energy security targets.

The Section 37 planning application for the Creagh Dhubh-Dalmally 275kV overhead line was submitted to Holyrood in early summer 2022.

In September 2022, Argyll and Bute Council’s Planning, Protective Services and Licensing Committee voted to raise an objection to the application, automatically triggering a Public Local Inquiry.

There were no other statutory stakeholder objections received.  

The impact of the Public Local Inquiry has delayed the connection of homegrown low carbon electricity generation across Argyll and Kintyre, increased the cost of the project due to supply chain and inflationary pressures, alongside significant legal costs for various parties, all of which will ultimately cost energy consumers, SSEN said.

It argued that the action strengthens widespread calls for reforms to our planning system to ensure the timely determination – within a maximum 12-month period – of the critical national infrastructure.

Director of capital development and delivery Tony Scott said: “We welcome the decision by the Scottish Ministers to grant consent for the Creag Dhubh-Dalmally 275kV overhead line. 

“As a responsible developer with decades of experience and expertise in developing transmission infrastructure, this decision demonstrates the robustness and professionalism of our development process.

“We also recognise that some in the local community may be disappointed by the decision and as we now look ahead to the construction phase, we would like to reassure the local community and wider stakeholders that we are committed to working with them to minimise any construction impacts, alongside engaging with businesses and other partners in the area to maximise the economic opportunities that our investments across Argyll and Kintyre represent.

“We also believe today’s outcome strengthens the widespread calls for reforms to our planning system to avoid unnecessary and costly delays. 

“Such delays are not in anyone’s interests, whether from the point of view of local jobs and investment, the uncertainty caused to communities, or of course in relation to critical national infrastructure projects that are essential to delivering a cleaner, more secure and affordable energy system for current and future generations.

“We now look forward to working with the local community and wider stakeholders as we prepare for the construction phase.”

Grid Scotland Scottish Government SSEN Transmission
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleBOEM unveils second Central Atlantic sale
Next Article ‘Renewables now 30% of US power capacity’

Related News

SSEN Transmission gains upgrades consent

December 17, 2024

Scottish Ministers approve grid upgrade

September 13, 2024

SSEN files needs case for Scots grid upgrade

May 31, 2023
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Pembroke Port
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}