Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » SSEN halts Scottish substation plan
Grid

SSEN halts Scottish substation plan

Eleanore RobinsonBy Eleanore RobinsonMay 21, 20253 Mins Read
Ofgem opens consultation on ‘Beyond 2030' projects

SSEN Transmission has announced it is no longer proceeding with Coachford substation to the south of Keith, part of the Beauly-Peterhead 400kV project. 

The decision follows extensive site surveys, including ground condition investigations, which have identified engineering and construction challenges with the previously proposed substation site, SSEN said. 

Despite finding unanticipated challenges at the Coachford substation location, the business has identified a solution that allows the objectives of the Beauly to Peterhead 400kV project to be maintained – and future network development to be delivered, it added.

Coachford was initially identified as one of four substations proposed along the route of the Beauly-Peterhead 400kV project, which is part of a wider programme of investments in the electricity transmission system across Great Britain that are required to deliver clean power and energy security targets.

Whilst the Coachford site is no longer being progressed, the wider Beauly-Peterhead 400kV project, and its initial objectives, remain on track for 2030 delivery.

Advertisement

A new substation in the wider area will still be required to support future network development plans, including a second subsea link from Shetland, in the early 2030s. 

Work will now commence to identify an alternative suitable site, where lessons will be taken from the extensive engagement and consultation undertaken during the development of the Beauly-Peterhead project.

Nick Brown, development portfolio manager at SSEN Transmission, said: “After carefully considering a number of options, we will no longer be proceeding with the previously proposed Coachford Substation as part of the Beauly to Peterhead project and will be looking to deliver the initial objectives of Coachford at another site, associated with future network developments.

“Work to explore potential alternative sites will get underway soon, making use of the insight gathered to date from both community consultation and our site selection and development process.

“The Beauly to Peterhead 400kV overhead line project remains a critical infrastructure scheme designed to support the delivery of Scotland and the UK’s energy security and clean power targets.

“By 2030, we will now build three new substations rather than four – with alterations made to accommodate this change.

“Crucially, the proposals will still deliver the power transmission and grid connectivity requirements identified under our ‘Pathway to 2030′ investment programme.

“While the Coachford substation won’t now be built by 2030, a new substation in the area will still be required by 2033 to meet future network demands and reduce infrastructure impact.

“We will now actively explore alternative options to deliver the network capabilities originally planned at Coachford.

“That work will involve identifying potential new sites in line with ongoing and future network development needs.

“The company will build on the significant insight already gathered from the Coachford planning and consultation process, ensuring that lessons learned inform future site selection and design.’

The Beauly to Peterhead 400kV project is one of several being progressed as part of our £20bn ‘Pathway to 2030′ investment programme, which is crucial in delivering on Scotland and the UK’s energy security and clean power targets.

Grid Scotland SSEN Transmission Transmission
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article‘Signs of retreat from floating wind’
Next Article Orsted installs final Greater Changhua 2b foundation

Related News

Ofgem backs early construction cash for transmission work

November 19, 2025

SSEN Transmission unveils new £17m warehouse

April 8, 2025

SSEN Transmission launches community benefit fund

November 25, 2024
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • TGS
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}