Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » UK to streamline process for wind farm permissions
Other News

UK to streamline process for wind farm permissions

reNEWS EditorialBy reNEWS EditorialMarch 11, 20253 Mins Read
UK climate watchdog urges net zero course correction

Consultation requirements for UK wind farms will be streamlined to speed up project delivery, under measures outlined in the government’s Planning and Infrastructure Bill.

The bill, which was formally introduced to Parliament today, will see significant measures introduced to speed up planning decisions and remove unnecessary challenges to the delivery of vital developments such as wind farms, roads and railway lines.

Advertisement

The government wants to create a faster regime for National Significant Infrastructure Projects (NSIP), enabling speedier project delivery.

The new NSIP regime will streamline the consultation requirements and ensure the national policies against which infrastructure applications are assessed are updated at least every five years so the government’s priorities are clear.

There will also be an overhaul of the process by which government decisions on major infrastructure projects can be challenged.

Meritless cases will only have one – rather than three – attempts at legal challenge, to help minimise delays. 

Data shows that over half – 58% – of all decisions on major infrastructure were taken to court, including wind farms in East Anglia, which were delayed by over two years as a result of unsuccessful challenges.

The bill will also allow clean energy projects, including wind and solar developments, to jump to the front of the queue for grid connections.

Some projects currently face waits of over 10 years. A ‘first ready, first connected’ system will replace the ‘first come, first served’ approach to prioritise projects needed to deliver clean power.

The bill comes alongside wider planning reforms including the new National Planning Policy Framework and is at the heart of the government’s Plan for Change mission to ensure Britain can become a clean energy superpower.

People living near new electricity pylons will also receive up to £2500 over 10 years off their energy bills.

Around twice as much new transmission network infrastructure will be needed by 2030 as has been built in the past decade.

Other measures outlined in the bill include an extension to the generator commissioning period from 18 to 27 months to reduce the number of offshore wind farms requiring exemptions when applying for licences to connect to onshore cables and substations.

Reacting to the bill, LCP Delta said it was vital to speed up transmission network infrastructure and clear the backlog of new energy projects struggling to connect to the grid.

Head of energy economics, policy and investment at LCP Delta Sam Hollister said: “There are serious concerns for new energy projects struggling to connect to the grid that could endanger the UK’s Clean Power 2030 targets.

“Currently, the grid connections queue holds a capacity of 750GW across transmission and distribution networks, damaging investor confidence and hindering the completion of valuable clean energy projects who are struggling to get connected.

 “The time to overcome this barrier is now.

“A turn towards a ‘first ready, first connected’ system to deal with these backlogs should be welcomed by developers and investors focused on unlocking the economic potential of grid decarbonisation.”

clean energy government Grid grid connection net zero Offshore Wind Onshore Wind Plan for Change Planning and Infrastructure Bill Renewable energy news Solar UK UK Government
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleRPC picks contractors for Finnish BESS
Next Article RWE cuts US offshore workforce

Related News

UK Planning and Infrastructure Bill comes into force

December 18, 2025

UK reforms to fast-track onshore wind projects

October 14, 2025

UPDATE: UK Energy Bill introduced to Parliament

July 6, 2022
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • Seaway7
    Seaway7
  • Pembroke Port
  • Ørsted
  • Navantia Seanergies
    Navantia Seanergies
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}