Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Low Carbon launches second 500MW PV consultation
Solar

Low Carbon launches second 500MW PV consultation

SaraBy SaraJune 22, 20222 Mins Read
Aura Power seeks planning consent for 50MW UK solar

Low Carbon has launched its second consultation on refined proposals to build a 500MW solar park and energy storage installation in eastern England.

The consultation on the project at Gate Burton, in Lincolnshire, will run from 22 June to 5 August 2022.

Advertisement

During this time, Low Carbon is asking for the views of communities living close to the site as well as those from the wider area.

The consultation precedes Low Carbon submitting its application for development consent to the Planning Inspectorate.

Comments will be invited on topics including the updated masterplan, visual impact considerations and the electrical connection into the national grid at Cottam substation.

Low Carbon will also be asking people for their views on how community benefit initiatives linked to Gate Burton Energy Park could be administered and managed, as well as for further suggestions of local projects and community initiatives that could be supported.

Mike Rutgers, development director at Low Carbon, said: “This is a major milestone for Low Carbon as we approach our planning submission.

“We’ve taken into consideration the feedback provided by the local community earlier this year which, alongside our ongoing technical and environmental surveys, has helped us to refine our proposals to those you see today.

“The community asked us to work with other developers in the area to reduce cumulative impacts.

“You’ll see from our new plans that we’re proposing to do just that. By seeking to align our Grid Connect Route with other proposals in the area, we hope to pursue the most efficient way of working and minimise any adverse impacts on the community.

“We’re looking forward to meeting the local community again in the coming weeks and explaining the measures we’re proposing to ensure Gate Burton Energy Park sits sensitively in the local landscape, preserving wildlife and habitat.”

The land outlined for Gate Burton Energy Park is in the West Lindsey District near Gate Burton, Knaith Park and Willingham-by-Stow.

The onsite energy storage system would provide a balancing service for the national grid.

This would allow the renewable electricity generated by the panels to be stored on site at the times when grid-demand is low and then exported at times of higher demand, maximising the contribution of renewable energy to the national grid, and in turn, helping to address the climate emergency.

Low Carbon Solar
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous Article‘Industry must eschew push for bigger turbines’
Next Article Wind and biodiversity ‘must go hand-in-hand’

Related News

Banks Group sells 2.9GW UK BESS project

October 9, 2023

UK developer all ears on 500MW PV-plus-storage

January 11, 2022

500MW solar park planned for Lincolnshire

October 13, 2021
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Collett & Sons Ltd
  • Leask Marine
  • Seaway7
    Seaway7
  • Qualsurv Marine Consulting
    Qualsurv Marine Consulting
  • Natural Power
    Natural Power
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EEW
    EEW Special Pipe Constructions GmbH
  • EDF
    EDF
  • Bilfinger UK
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}