Close Menu
reNEWSreNEWS
  • Home
  • Offshore Wind
  • Onshore Wind
  • Solar
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
Latest News

PODCAST: Is UK offshore wind back on track?

All-Energy 2026: Shanks bullish on UK clean power

GWEC, TÜREB launch wind partnership

LinkedIn Facebook X (Twitter)
LinkedIn Facebook X (Twitter)
  • Email Briefings
  • About
  • Advertise
  • Contact
reNEWSreNEWS
  • Home
  • Offshore Wind

    PODCAST: Is UK offshore wind back on track?

    May 13, 2026

    UK offshore wind pipeline reaches 93GW

    May 13, 2026

    Seaway7 completes Hai Long cable works

    May 13, 2026

    DEME names new jack-up vessel

    May 13, 2026

    Mubadala invests $325m into Hornsea 3

    May 13, 2026
  • Onshore Wind

    ENERCON to build Türkiye blade plant

    May 13, 2026

    ‘Fatality at South Korean wind farm’

    May 13, 2026

    Scottish onshore wind forum launches

    May 12, 2026

    ENOVA starts 30MW Hiddels repowering

    May 12, 2026

    Iberdrola buys 40MW Italian wind farm

    May 12, 2026
  • Solar

    VSB secures Sicily PV project approval

    May 13, 2026

    Matrix connects two Spanish renewable projects

    May 13, 2026

    Qualitas targets €10bn energy investments

    May 12, 2026

    Consultation opens for 49.9MW Barrons Solar

    May 12, 2026

    Great North Road solar nears decision

    May 11, 2026
  • Other News
    • Energy Storage
    • Finance
    • Grid
    • People
    • reMIX
  • More
    • Company Profiles
    • Events
    • National Wind Energy Awards 2026
LinkedIn Facebook X (Twitter)
reNEWSreNEWS
Home » Uncategorized » Ofgem probes Gate 2 connection delays
Grid

Ofgem probes Gate 2 connection delays

Andrew FawthropBy Andrew FawthropFebruary 13, 20262 Mins Read
Ofgem probes Gate 2 connection delays

UK energy regulator Ofgem said it will be working with NESO and transmission operators (TOs) to “ascertain the causes of widespread connection date delays” following last year’s Gate 2 to Whole Queue grid reform process.

The organisation said it was notified by NESO and the network companies last June of risks that certain projects due to have existing connection dates in 2026-27 “protected” in the queue overhaul may not be able to retain their original network dates.

Advertisement

It said details have now been provided of the affected projects, noting 210 of the 340 schemes (62%) that qualified for protections will have their existing connection date and/or point of connection changed.

“Whilst our engagement with NESO and TOs into the reason for these changes continues, around 135 of these projects will have their connection dates delayed due to some form of network-driven reason (either solely or jointly with developer delays), with 75 of these projects having their connection dates delayed due to developer-driven reasons,” Ofgem stated.

“We are both frustrated and disappointed that it is not possible for TOs and NESO to meet existing connection dates and points of connection for all projects qualifying for this protection, particularly given the widely recognised importance of ambitious and reliable connection dates.”

Ofgem has urged NESO and the network companies to issue the Gate 2 offers “as soon as possible” and, in cases where dates must be delayed, to offer protected projects their “best view of the most ambitious date possible, which should be realistic, accurate, and made in good faith”.

Connections reform Grid NESO Ofgem
Share. Facebook LinkedIn Bluesky Twitter Reddit Email Copy Link
Previous ArticleETIC secures €70m first close for fund
Next Article DNV buys SPS to boost grid expertise

Related News

NESO issues first Gate 2 grid connection offer

February 18, 2026

‘Grid reform lifts confidence but hurdles remain’

December 8, 2025

NESO opens window for new grid connections

July 8, 2025
Advertisement

Latest News

PODCAST: Is UK offshore wind back on track?

May 13, 2026

All-Energy 2026: Shanks bullish on UK clean power

May 13, 2026

GWEC, TÜREB launch wind partnership

May 13, 2026

ENERCON to build Türkiye blade plant

May 13, 2026
Advertisement

Advertisement

Company Profiles
  • Leask Marine
  • Seaway7
    Seaway7
  • Pembroke Port
  • Oceantic Network
  • Natural Power
    Natural Power
  • LSP
    LSP Renewables
  • JDR Cable Systems Ltd
  • Full Circle Wind Services
  • EDF
    EDF
  • Brightwind
    BrightWind Limited
reNEWS
LinkedIn Facebook X (Twitter)
reMIX | Company Profiles | Industry Events
Get in touch | Advertising with us | About reNEWS

© 2026 Lewis Business Media. All Rights Reserved.
Lewis Business Media, Suite A, Arun House, Office Village, River Way, Uckfield, TN22 1SL

Terms and Conditions | Privacy Policy | Cookie Policy

Type above and press Enter to search. Press Esc to cancel.

Manage Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behaviour or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
  • Manage options
  • Manage services
  • Manage {vendor_count} vendors
  • Read more about these purposes
View preferences
  • {title}
  • {title}
  • {title}